Job: Temporary Excavation Support System - Soil Nails & Shotcrete

Stabilized the soil & utilities underlying the arena floor. This permitted placement of the indoor underwater treadmill adjacent to & below the arena floor in the locker room.  Soil Nail restricted access rigging (width & height) was through a 250 l.f. corridor and the pumping distance was 450 l.f.  Two pumps were used.

Project Spotlight: OSU Basketball Practice Facility - Men's Locker Room -  Columbus, Ohio

A 100 yard per hour pump inside the loading dock area was used to pump material 200'0" down a finished hallway into the locker room. A transfer pump was then used to pump the material another 150'0" to install the shotcrete.